Wednesday, August 9, 2017

8.9.2017

Another beautiful  day but another self-imposed rain, work inside day!  It's all worth it because the insulation details are really coming together!
 
Jim got the rest of the area around the attic door all finished...
 

 
And finished the little area at the top of the transition wall between the bedroom and kitchen.
 
 
He got the vent and fan sections all finished in the bathroom...
 

Jim also stuffed the tops of the studs that I worked on yesterday - that enabled him to put up the fiberglass today.


The knee wall in the laundry room is all done except for the part that has to remain open to do the dryer vent work.  Jim ordered a nice vent online so it should be coming soon.


He got plastic put over the section in the master bedroom that had been stuffed.
 

I worked on stuffing more of the studs in the wood shop with the loose cellulose insulation...


Jim did stuffing around the master bedroom window frames...


Doing the other window...

 
At the end of the day, Jim put together the drywall lift that he picked up last night.  We're making great progress so hopefully it will be put to use soon!


High 78/Low 56 - beautiful!


 

 