Monday, July 10, 2017

7.10.2017

Jim tackled a couple fronts this morning - he put the shower valve all back together.  The only thing he needs to do is crimp the Pex on and it will be time for testing again.
 
Then he started putting together the bandsaw - it's been here so long he wanted to make sure he wasn't missing any parts and pieces.  He reoriented its position and got the assembly started.
 

After lunch, it was time to work on shingles again.  Things are a bit slower now because of the scaffolding position - Jim has to keep moving from outside to inside the scaffolding as well as move all his tools.


Progress means time to move scaffolding - this time it's the side pieces.


Next, Jim made and installed the corner trim flashing...


More marking.  This is a little more complicated to make sure everything lines up since the utility box separates the two sections.


Making good progress...


End-of-the-day picture!


Then Jim put his mechanic hat on and worked on assembling the power steering pump.  He just about has it ready to go in the car.

High 81/Low 63