Wednesday, May 20, 2015

5.20.2015

Jim headed out to the land this morning to work on more scaffolding and shoring.  He got all of the cold-formed steel supports at the end of each stringer.

 
The replacement scaffolding arrived today too.  They didn't have an order to pick up the bad pieces so that will be another phone call.
 
 
Jim got all the rest of the little pieces of conduit cut and in place on the deck.  After lunch, I glued them all down - that job can be crossed off now.
 
 
When Jim went to the plumbing supply store yesterday, they didn't have one of the parts he needs to complete the sewer stack.  It came in today, so I headed to Saratoga to pick that up.
  
Jim has all 6 of the towers built now.  Here's an example of  one of the secondary shoring posts that will be at the ends of each of the scaffolding towers, attached to the stringers at  the top.
 

High 59/Low 40
 

 

 