Monday, October 17, 2022

10.17.2022

Jim started the day with a visit to the ophthalmologist for his biannual comprehensive eye exam - he got great results so we're very grateful for that!

Once he got home, he finalized bleeding the air out of the heating lines today and then put the baseboard units back together.  While he was hanging over the toilet, he cut off the bolts so that the plugs sit flat (one of those details that just gets pushed aside for important things!).


Jim continued working on all the steel fabrication and millwork for the package box...


He started fabricating the cross bars - cutting the pieces and doing the millwork.  He used the vertical drill press/mill to notch each piece - these will go upside in this frame to mate with the flanges of the cross pieces...


High 47.7/Low 34.9