Our sand was delivered early this afternoon...


Our new sand pile!


Jim spent this very cool and windy day working on all the shoring for the pour stops.  He got it all done for the pour stops that he has attached.  He still has to do the other end, but that requires a different approach - the pour stop has to be welded to the beam.  Since we still have an open trench and can't get the welder back to the building, that has to wait.


Here's the completed back section...

 
High 42/Low 30 - windy and cold
 