As always when confronted with an issue, Jim figures out a way and starts again.  So it was with attaching the meter boxes.  He's got them up now but also ordered some brackets to do even a better job.  They look good!


After that was done, Jim dug the trench from the back of the transformer box up to the front of the pedestal.  He has to get wire and this is heavy-duty, expensive cable.  This way, he can put a string in the trench and exactly measure how much cable he'll need.


Then it was back to digging - Jim and I kind of take turns operating the stick to see how accurate the footer levels are.



I did some more crumbing today to clean out the areas that Jim dug.


The birds-eye view of our footers.  The back wall with all its steps is now finished.  It looks even better than this picture now because after I left, Jim stayed and moved the dirt out of the middle of the site.