Saturday, November 22, 2014

11.22.2014

Jim spent some time getting the lot ready for the septic tank delivery - like moving some of the steel decking pieces we had stored nearby, moving the truck out of the way, and then moving our rebar pile.  Thankfully, he was able to use the forks on the Bobcat to pick up the rebar. 


Then we moved the cradles that the rebar sits in to a spot in front of the bricks - then he lowered the rebar back in place.

He also crumbed out the big hole for the tank and then we marked the area for the distribution box.  We also got the laser level back out and pounded a stake in the bottom of the hole to mark how deep the gravel needs to be so that the tank will sit at the proper level.


Then it was back to digging for the distribution box.

 
It was still a cold day, especially so once the sun disappeared behind some clouds in the afternoon.  We had decided to go to church in the afternoon and it started to sleet/drizzle a bit as Jim was cleaning up, so we called it a day.
 
High 35/Low 31


No comments:

Post a Comment