Wednesday, October 28, 2020

10.28.2020

It was back to plastering in the stairwell today but Jim is doing touchups now and working on the landing area - skim coating is getting closer!


In the afternoon, Jim concentrated on doing some electrical work.  He had to first remove the drywall from this area next to the breaker box.  He used his fish tape to go from the conduit at the bottom out to the pole barn; we're going to measure the length tomorrow so he can get started on putting the wire through.


Out in the pole barn, he mounted another box in the attic - the plan is to have two light fixtures up in the attic as well as one in the main barn, as well as one receptacle near the man door.


He ran wire down from the attic to the box by the door...


We also continued doing some work on sorting through our stored boxes.  Jim emptied and moved the old TV cabinet to the back wall and started stacking things on top...


High 47/Low 36 - light rain/drizzle